|
Construction of the Gibbs Street Pedestrian Bridge is a longstanding priority for community members in
the South Portland Neighborhood (formerly the Corbett/Terwilliger/Lair Hill neighborhood). This
pedestrian and bicycle bridge will provide safe and convenient access between these neighborhoods and
the Willamette River and the emerging South Waterfront District. The City of Portland has received
funding from the Federal Highway Administration to design and construct this important bike and
pedestrian connection.
Before 2008
The first concepts for the pedestrian
bridge were identified by participants in the international competition to design the Portland Aerial Tram.
In 2006, the City hired a consulting firm to refine the bridge design. This process gathered more input
from the public on aesthetics and concluded with the identification of a bridge concept that was acceptable
to the community and the City, but that probably could not be constructed within the $7 million construction
budget. View the background materials, including previous
public comments and conceptual designs.
In 2008, the City hired a consulting team headed by CH2M HILL to build upon the previous work and collaborate
with the community to design a preferred bridge concept that meets the project’s requirements and can be
constructed within budget.
Detailed design and engineering work was completed, as well as obtaining environmental permits to prepare for construction.
Construction began in January 2011. Photo simulations are available in the project library.
Pedestrian Crossing Improvements will be included as part of the Gibbs Street Pedestrian Bridge project. These
are proposed at Naito Parkway, SW Barbur Boulevard, SW Corbett, and SW Kelly.
More information on these concepts is found in the background materials section of the project library.
Since 2008
With input from the Citizen’s Advisory Committee, the City selected a bridge type for the
crossing; Steel Box Girder. In addition, the city made other changes to
the overall design including a simplified elevator and stairway design and one elevator instead of two.
The consultant utilized an independent cost estimating firm with experience in the local
construction industry to assist with the estimating, construction methods and other potential cost
savings to be able to bring the project design within budget.
The design team worked on the design, along with several meetings with the
Design Commission and South Portland Neighborhood Association. The City hosted an Open House in
June 2010 (read more on the Get Involved page).
Construction
The project was advertised for construction in September 2010 with a bid opening on
October 28, 2010. The construction contract was awarded to Wildish Standard Paving Co., a Eugene-based company
with experience building roads and bridges throughout the Pacific Northwest. Their bid was $6.7 million
compared to the engineer's estimate of $8.1 million.
Construction started in January 2011 and should be finished around March 2012.
Check the Project schedule
for more details about the current construction activities.
back to top
|